Greenfield Facility Improvements & Renovations Update

Greenfield Facility Improvements & Renovations Update

Work continues to be performed in phases with a portion of the men’s locker room reopening mid-December.  The spa room construction has begun and is scheduled to be completed late-December.  During this time, the dry sauna will be getting new tile on the floor and new wood on the walls/ceiling; the steam room and inhalation room will both be getting new tile on the floor/walls/ceiling and a new composite bench; the entire room will be getting a new ceiling and tiled flooring; and new drain grates will be installed in each area.  For those who like to use the spa room, you are welcome to visit the McCordsville facility to enjoy our hot tub, saunas and steam rooms.